Infrastructure, networks & security
Fitting out Ernst & Young's new offices in Cameroon and Chad
Ernst & Young · Cameroon and Chad · 2013–2014
Outcome: two turnkey offices delivered, with network, security, fire detection and server room ready for staff to move in.
- Challenge
- Ernst & Young was opening new offices in Cameroon and Chad and needed network, safety and IT infrastructure meeting group standards as soon as staff moved in.
- Scope
- Two offices, in Cameroon and Chad: network cabling, CCTV, fire detection and server room.
- Approach
- Cabling and layout design, coordination with the office fit-out, installation and testing of each work package, then commissioning of the server room.
- Deliverables
- Certified structured cabling, CCTV system, fire detection, fitted server room (racks, servers) and acceptance documentation.